Do we have a Definition of Ready (DoR) and Defintion of Done in Kanban?

Funny you should ask – this ties in nicely with the topic of explicit policies.

Here is a short answer regarding DoR and DoD

Conceptually speaking, every station in a workflow has either implicit or explicit entry and exit criteria. The notion of a DoR and a DoD (as they have become widespread in the Scrum community, even though the DoR is not really part of Scrum [1]) is modeling exactly this: having explicit entry and exit criteria for a system with one station.

When modeling a system with Kanban, those definitions for ready and done really need to become part of the often mentioned explicit process policies.

An Example

Let’s take a look at a simple example.
Assuming we have two stations A and B –where work flows from A to B– we look at B first, honoring the principle that we work on Kanban boards starting at the point closest to the value generation: the customer facing side.

|    station A   |    station B     |
|  doing | done  |  doing  |  done  |
|        |       |         |        |
|       / \      |        / \       |
|      /   \     |       /   \      |
|     /DoR B\    |      /     \     |
|    (   ⊆   )   |     ( DoD B )    |
|     \DoD A/    |      \     /     |
|      \   /     |       \   /      |
|       \ /      |        \ /       |
|        |       |         |        |
|        |       |         |        |

In this scenario the “Definition of Ready” (the entry criteria) for station B has to be part of the “Definition of Done” for station A. Why? Well, the “Definition of Done” for station A is the DoD for the Doing column of station A. Once a work-item leaves the “Doing” column nothing should be done with it – after all it has left one Doing column and not yet entered another Doing column.

Therefore when B pulls an item it will – or at least should – be exactly in the state it was when it left the Doing column of station A. That being said, there may of course be additional rules governing the entrance to station B (e.g. if the item is part of a multi-part workflow).

For the topic under consideration “Do we have a DoR and DoD in Kanban?” the short answer would be “yes”.

Scaling up

In any life-size system, where we have more that two stations, multiple sets of entry and exit criteria make sense – one set per station (column). Whether we focus on the DoR or on the DoD first, is a matter of focus. Both approaches might be appropriate.

Taking this further, beyond A and B we get something like:

|    station A   |    station B     |   Station C    |…
|  doing | done  |  doing  |  done  |                |
|        |       |         |        |                |
|       / \      |        / \       |                |
|      /   \     |       /   \      |                |
|     /DoR B\    |      /DoR C\     |
|    (   ⊆   )   |     (   ⊆   )    |     . . .
|     \DoD A/    |      \DoD B/     |
|      \   /     |       \   /      |
|       \ /      |        \ /       |
|        |       |         |        |
|        |       |         |        |

From my experience, it is helpful to start thinking this through from the right hand side and consider the DoRs first. But then again life is complex and depending on your actual situation there may be other approaches that make sense.

Ceterum censeo: Of course we can model everything we have in a Scrum process with a Kanban system. Both operate at different levels and Kanban is meant to be able to model existing processes. The question whether you should move from one to the other is non-sensical by definition but conversely adding Kanban to Scrum actually makes a lot of sense.

Cheers
Michael

[1] The Concept of a DoR is actually only sometimes helpful. The more current versions of the Scrumguide just contain the line "Product Backlog items that can be Done by the Scrum Team within one Sprint are deemed ready for selection in a Sprint Planning event." The term "Definition of Ready" is only used in secondary literature.

Sunday, March 05, 2017

The "definition of done" for life...

...would be a scary thing, wouldn’t it?

Yet people often ask me “When will we be done with the change?” or “When will our working agreements (sometimes also called processes) be finished?”

But that’s just the thing. In an ever changing world neither working agreements nor processes nor environments can ever be finished. In our lives we don’t try to get to the finish – I, for one, actively try to avoid that for as long as possible. Most of us just have a life. One that is well suited to whatever the environment throws at us.

For me the question is not “When will the change be over?” but “which change do we need right now?”.

till next time
  Michael Mahlberg

P.S. It’s not the finish it’s the journey. Or, to quote somebody else:

Life is not a journey to the grave with the intention of arriving safely in one pretty and well preserved piece, but to skid across the line broadside, thoroughly used up, worn out and loudly proclaiming -- WOW-- What a Ride!
~ Paraphrased after Bill McKenna, professional motorcycle racer