Sunday, July 26, 2015

Sprints – Give me a break

An iteration in Scrum is called a sprint ...
Scrum is at least six years older than the agile manifesto ... The Agile manifesto’s principle 8states that “[everybody] should be able to maintain a constant pace indefinitely.”...

How does this compute?

Sprints are related to Scrum

First of all let's re-iterate a well-known fact that often gets overlooked anyway: Scrum is not agile. WHAT? Of course Scrum is an agile Method! But that relationship has a direction. Speaking in terms of set theory what I am getting at is the fact that Scrum is just a Subset of "Agile." Looking at the history of Agile, Scrum is just one of the contributing methodologies that were instrumental in defining "Agile" (via the Agile Manifesto). And in Scrum – if you have read the old book by Schwaber and Beedle – the Idea of the Sprint was "to be able to work un-interrupted towards an agreed upon goal" (paraphrased). With these bounding conditions it makes sense to talk about a sprint, where you look neither left nor right, but focus only on the problem at hand. As long as you are sure that you are able to deliver a “potentially shippable product increment” at the end of the sprint (and not some loosely related artifacts that might be welded together in an upcoming future sprint).
But the metaphor only goes so far – the way I understood it from Ken back in 2005 and try to live it these days – sprinting here mostly refers to the focus on the sprint goal, not to the total exhaustion one would deem acceptable for winning the gold medal at a 100m sprint at the Olympic Games.

Sustainable pace is related to XP

The principle of “sustainable pace” comes – almost verbatim – from eXtreme Programming's definition of this XP "Rule" of set(ting) a sustainable pace. Here the focus actually was on not exhausting ones resources. And no, a resource in this context is not a human being, but a persons mental and physical energy reserves and such – just in the same way a marathon runner uses the phrase “at 35k I just had no resources left.”

All models are wrong - but some are useful!

"Sprint" is a Token, a word that identifies an artifact in the Scrum framework. It happens to be a metaphor as well. Metaphors only translate into different domains so far. As pointed out by the aforementioned quote some models are useful. And to me the Sprint-model is useful with regard to the focus on the next goal, not with regard to the total exhaustion of ones resources.

Your mileage may vary of course, but I think that decomposing the different aspects of the metaphor helps a lot in deciding how to live those aspects in your concrete situation.

So long,
    Michael

Sunday, April 20, 2014

Remember: to backlog (verb) means ‘to pile up’…

And the noun means

2. an accumulation of tasks unperformed []…“ – Merriam-Webster online dictionary

Translating the word to German makes it even worse: According to dict.cc amongst the German translations there are:

  • Rückstand (lag, deficit, handicap)
  • Nachhohbedarf (a need to catch up)

So clearly there are some negative connotation with regard to the term backlog. Still it has become a term with positive connotations in the software development community within less than two decades.

Yet –regardless of the positive connotations–, time and time again I see backlogs used in a way that seems counterproductive to me, Accumulating more and more “undone work” in the “backlog” - whether it is called backlog or feature-list or ticket-store or any other name.

In these cases, the items in that list really become a “Rückstand” as we would say in Germany - a lag with a need to catch up!

Of course there are several countermeasures to this – Backlog Grooming probably being the best known. But lean approaches also point to another idea on how to handle this: be very well aware of what your backlog really is and what you commit to!

Backlog vs. Ready-Column

Little’s law tells us that the average time an item spends in the system is determined by the work in progress divided by the time it takes to work on one item.


If we trust in this formula, basic mathematics tell us that if we put infinity in the numerator the result will also be infinite.

Thus, if we don’t put a limit on our backlog, we do not have a predictable time to completion.

Let‘s draw a picture of that:

Very often task-boards, scrum-boards, informal kanban-boards etc. are organized like this:


An unlimited input column (in Scrum for example it is the product-owner‘s job to keep the backlog prioritized the right way, resulting in an ample amount of preselected work for the next iteration), followed by some columns for the different stations in the process and finally an unlimited column for the finished work. While one might argue about the last one – which would make a good topic for a post on it‘s own – in general there is nothing wrong with this setup.

The problem arises when people forget that they can‘t make predictions about the whole board. Since the first column is endless (i.e. not limited) the average time any item spends in the system implicitly also goes towards infinity.

Now for the simple solution:

Only promise what you can control!


Without changing even one stroke on your board, just by communicating clearly that the predictability begins where the control begins, a significant change in expectation management might occur.

(Of course this was originally part of most agile approaches - it just happens that nowadays it seems to be forgotten from time to time…)

Shifting to an input queue

While we‘re at it: Why not change the wording to reflect the difference? While a _‘backlog’_ is a – potentially endless – list of things ‘not yet done‘ what we really want to talk about is a list of thing ‘to be done in a foreseeable, defined future‘. For me, one term that captures this concept nicely is the _‘input queue’_ – a term frequently in use in the lean community. And while I‘ve seen many (product-) backlogs without a limit, I have not yet come across an input-queue without a limit.

’till next time
  Michael Mahlberg

Sunday, March 23, 2014

In Kanban the kanban is not the kanban - What?!?

In Kanban the kanban is not the kanban - What?!?

In the early stages of the introduction of Kanban systems many organizations struggle with the implementation of the pull signal and how the cards represent the pull signal.
In my experience a lot of this confusion is caused by semantic diffusion and the fact that “The Kanban Method” (for software development and other knowledge-work) often gets over-simplified and is reduced to a lax translation of the word kanban and the original 3 rules for a Kanban (capital K) system.

Basics

Let’s look a bit deeper into this
As David Anderson points out in his famous blue book the word kanban means (more or less) «signal card» and such a card is used to visualize a so called pull request in a traditional kanban environment.

Now there is a lot of information put into one little sentence. What is a traditional kanban system anyway? What is a pull request? And what’s different in our Kanban (capital K) systems?

A “traditional” kanban system is the kind of kanban system that has been in use at the production plants of Toyota and the like to optimize the flow of physical work products through the factory. Here the upstream station – that is, any station that lies before another station in the value stream – gives out kanbans which represent their capacity. These kanbans act as tokens for the downstream stations to request new material – or, to pull the material.

But what is different in “our” Kanban systems? Well, the reaon for the capital K is the fact that we’re working with a different kind of representation in “The Kanban Method” (for software development and other knowledge-work). On page 13 of the aforementioned book David points out that

«… these cards do not actually function as signals to pull more work. Instead, they represent work items. Hence the term ‘virtual’» (emphasis mine)

Virtual pull signals

So what about the pull signal in this scenario? Isn’t it all about establishing a pull system? Well, it’s covered in work. Literally. Almost. But at least it can be covered by work as the following illustration shows.

A very simple board

A kanban board in use

Some work moved

A kanban board in use

More work moved

A kanban board in use
As you can see: you can’t see any pull signal - only the work.

That’s because the pull-signal is actually hidden behind the work and not really visible. At least not in this rendition. It is possible to make it visible, but only for very simple boards. All that’s needed here is a little annotation.

A very simple board with annotation

A kanban board annotated with pull signals
A kanban board annotated with pull signals…

Board filled with work

An annotated board in use step-1
The same Kanban board in use – all the pull signals hidden by the work. Looks quite similar to the non-annotated board, doesn’t it?

Some work moved into production

An annotated board in use step-2
So now, when the cards are moved, the pull-requests become real visual signs.

Work getting pulled all over the board

An annotated board in use step-3
And when the pull-request are fulfilled, that in turn reveals more pull requests and so on.

A more complex board

Actually most evolved Kanban board contain at least some queue-colums - often differentiating between “doing” and “done.” Now the annotation approach doesn’t work any more because the pull signal becomes completely virtual.

Let’s have a look at this as well.

The same work on a more elaborate board

Board with explicit “done” columns
Work in progess shows up in the doing colums of course

Some work is done

Board with explicit “done“ columns after some work is done
Even though some cards are moved around, no WIP-Limits are broken and no pull request issued (WIP-Limits in this example go accros doing and done)

Invisible pull signal

A pull signal is implied but not visible yet
Now that a work-item has left its WIP-boundaries a pull request is implied - but not at all visible.

Virtual pull request

The pull signal in Numbers
In fact the pull-request is only ‘visible’ by comparing the actual Work-In-Progress – in this case 2 – with the WIP-Limit, which is (3) in this example. Hence the pull request can be calculated but is not visible to the naked eye. Which fits in nicely with the notion of a “virtually signalled pull request”. This can be translated to “virtual kanban”. And of course virtual kanbans live on ”virtual kanban boards” in “virtual kanban systems”.

’till next time
  Michael

Sunday, February 23, 2014

Blocked by multitasking

Blocked by multitasking!

Teams who struggle with delivering software seem to share one common characteristic that has turned out to be a recurring theme in my consulting work - the tendency to multitask.

As I mentioned earlier it is very easy for a team to be busy all the time – even so much that they might be on the verge of a breakdown – while a lot of the work products go stale because they sit around idling for extended periods of time.

Chris Matts and Olav Maassen do a wonderful job of debunking the myth of «effective multitasking» in their graphic Novel Commitment. When they talk about hidden queues they explicitly mention that multitasking is just that - a queue of things unfinished. In fact, at least from my experience, the queues created by multitasking with the best of intentions (I can't finish task A so I'll just start on task B until I can work on task A again so that I don't have to idle an burn precious development time) are much worse than defined queues in the process because they tend to be barely visible. On one hand these concealed queues hide the fact that Task A is blocked. On the other hand the have to be managed in the back of the head which adds to the cognitive burden of the person working on the task(s). This more often than not this leads to “I can't finish task L so I'll just start to work on task M... oh, wait task D seems to be workable ... hmm but so is task H ... ”.

So, if you want to do yourself and you colleagues a favor, please apply the hackneyed but true optimization rule to multitasking: "Don't do it" ... or switch to the advanced Version of that rule "Don't do it – yet".

Make blockers – which would drive you to multitask – explicit and squelch them as soon as possible. And visualize any kind of queue you start to create, so that you and others can manage it.

'til the next time
  Michael